A 6 days turn-key kettle change: keeping it simple.
California, USA
250,000 LBS
When Zinco is coordinating a turn-key project, efficiency is center stage.
A complete kettle change needs to be performed shortly after Christmas, while holidays are in full blast. Production must be restarted as soon as possible and all subcontractors need to be coordinated.
Zinco gets involved to plan the project months in advance. Together with the Customer, information and technical data are exchanged. An official planning is edited and discussed with all the involved contractors. The expertise accumulated in projects around the World helps Zinco tailoring a solution to the needs of the specific site. This means choosing the best kettle extraction procedure and making sure power supply and furnace materials will be available exactly as needed. The result? A project running ahead of the official schedule, a great result and a happy Customer.